Chinese New Year 2027: An Amazon FBA Inventory Plan and Deadlines

Pouyan Pazargadi
Pouyan Pazargadi

This week, most Amazon sellers are thinking about Black Friday and Cyber Monday. But if you buy inventory from factories in China, the decision that shapes your February and March sales is happening right now, not in the new year. Chinese New Year 2027 falls on Saturday, February 6, which is 11 days earlier than in 2026. Factories slow down weeks before that date and take weeks to get back to full speed afterward.

If your last order before the break is too small or too late, your best seller can go out of stock in late February, and the next container may not reach Amazon until spring. This guide explains the 2027 dates, a backward calendar for US FBA sellers, the questions to ask every supplier, a simple formula for how much to order, and where to keep the extra stock so Amazon's fees and capacity limits don't eat the benefit. Dates and ranges below come from logistics providers and published guides, so treat them as planning estimates and confirm the real dates with your own supplier and freight forwarder.

📦

Free Download: The Amazon FBA Starter Checklist

A smooth restock starts with a supplier and a shipping plan you can trust. This free checklist helps Bubba Academy students choose products carefully, vet suppliers, and prep a clean first FBA shipment.

  • ✓  Step-by-step product selection framework
  • ✓  Supplier sourcing and negotiation checklist
  • ✓  First FBA shipment prep guide
Download Free Checklist →

Chinese New Year 2027: The Dates That Matter

China's State Council published the official 2027 holiday schedule in November 2026. According to the State Council notice, the Spring Festival holiday runs from Friday, February 5 (Lunar New Year's Eve) to Saturday, February 13, a total of nine days. Sunday, January 31 and Sunday, February 14 are make-up workdays. Maersk's 2027 peak season calendar confirms New Year's Day is February 6, the start of the Year of the Goat.

The official holiday is not the factory calendar

Nine days sounds manageable. The real disruption is much longer, because hundreds of millions of workers travel home and many factories close around that trip, not around the official dates. Maersk notes that factories may start reducing output in the weeks before the holiday and can take several weeks to return to normal afterward.

The ranges reported by logistics firms are wide:

  • The Loadstar reported that suppliers Seko works with in northern China were planning a January 25 to February 15 shutdown, while some southern China operators expected to stop three weeks before the festival and need about two weeks after it to reach full production.
  • China Quality Service lists Thursday, February 4 as the practical last working day in most factories, a typical stop-work window from mid-January to mid-February, and a return to full capacity from late February to early March.
  • PrepVia, an FBA prep center, plans for six to eight weeks of disrupted supply: three to four weeks of hard closure followed by three to four weeks of reduced output.

Why 2027 is tighter for Amazon sellers

An early February holiday pushes the pre-holiday shipping rush into January. That overlaps with the busiest stretch of the Amazon year for many sellers: holiday returns, the cash gap after the fourth quarter, and January restocks. The Loadstar quoted a Seko customer who raised purchase orders three weeks earlier than usual so they would not end up at the back of the production queue.

A Backward Calendar for US FBA Sellers

Container ship and orange cranes at a busy shipping port at dusk

The useful way to plan is backward: start with the date your inventory must be sellable at Amazon, then subtract receiving, freight, export, and production time. Forceget, a freight forwarder, published this timeline for FBA sellers on November 24, 2026:

WhenWhat it means for FBA sellers
November to early December 2026Last purchase orders that can be produced before the closure. Get supplier dates in writing.
Mid-December 2026Last ocean space booked; rates rise. Create the shipment plan.
Late December to first week of JanuaryLast ocean departures. Less-than-container-load (LCL) closes first; full containers around the first week of January.
Second half of January 2027Factories slow and close. Only air and express remain, at peak rates.
February 5 to 13, 2027Official holiday.
Mid-February to March 2027Factories restart with reduced staff. First new orders reach FBA in late March or April.

Forceget sums it up this way: inventory you need in February and March must leave China by the first week of January by ocean, or by late January by air.

West Coast and East Coast deadlines are different

Your destination port changes the math. China Quality Service gives these planning estimates, and stresses that you should confirm them with your forwarder:

  • US West Coast (Los Angeles / Long Beach): about 14 to 18 days of ocean transit, with a latest vessel departure around January 21 to 24, 2027.
  • US East Coast (New York / Savannah): about 30 to 35 days via the Panama Canal, with a latest departure around December 27, 2026 to January 4, 2027.

Remember that the port is not the finish line. Customs clearance, trucking, prep, and Amazon receiving all come after the ship arrives. If your goods usually take two weeks from port to "available" in Seller Central, add those two weeks before you count on the stock.

Book freight early, and add slack

Freight tightens before factories do. Seko told The Loadstar it recommends placing ocean bookings at least four weeks in advance, notes that carriers typically add blank (cancelled) sailings around the holiday, and suggests building one to two extra weeks into transit plans. iBanFirst suggests many importers request transport capacity four to six weeks before the shipping date they want.

Ask Every Supplier for These Dates in Writing

Every source above agrees on one point: the public holiday calendar is only a starting point. Each factory sets its own schedule, and some workers do not come back after the break. iBanFirst recommends asking each supplier to confirm:

  1. The last date they will accept new orders
  2. The last date they can start production
  3. The date the factory closes
  4. The expected reopening date
  5. The date full production is expected to resume
  6. Whether staffing levels will change after reopening
  7. The last date goods can ship before the holiday

Send these questions now, even if you think your current order is safe. A supplier who says "no problem" in November may be juggling many rush orders in January. Ask for the dates in a message or in the purchase order itself, so you have something to point to later.

Put the riskiest products first

iBanFirst suggests giving priority to products with long manufacturing lead times, single-source items, critical components, and goods with few substitutes. For an Amazon seller, that usually means your best sellers and any product whose packaging, inserts, or custom parts come from a second supplier. If one component is late, the whole order is late.

🗓️

Plan Inventory Around the Supplier Calendar

Lead times, freight, and Amazon's inventory rules all shape how much stock you should order. Bubba Academy's step-by-step program shows sellers how to source products, plan shipments, and keep listings in stock.

  • →  A clear roadmap from listing to first sales
  • →  Fees, pricing, and promotions explained in plain language
  • →  Learn from sellers who have launched real FBA products
Start with Bubba Academy →

How Much Inventory to Order Before the Shutdown

The normal reorder math still works. The difference is that lead time gets much longer, because no new production leaves China for several weeks. If you want a refresher on the standard formula first, our guide to the reorder point formula for Amazon sellers walks through it step by step.

The pre-holiday formula

Forceget offers a simple version for the Chinese New Year order:

Pre-holiday quantity = daily sales × (factory gap + transit time + safety margin) − (stock at Amazon + stock already on the way)

In its example, a product selling 20 units a day, with a 56-day factory gap, 45 days of door-to-door transit, and a 14-day safety margin, needs 20 × 115 = 2,300 units. With 400 units already at Amazon, that leaves 1,900 to order before the holiday. Your numbers will be different, so run the formula for each SKU rather than copying the example.

Use last February's sales, not this December's

Forceget points out a common mistake: using December's holiday sales rate to plan for February and March. Look at your daily sales for the same weeks last year and adjust for growth. If the product is new, use a conservative estimate. Forceget also notes that the Restock Inventory page in Seller Central can suggest quantities, but it does not know when your factory closes, so treat it as a check, not the answer.

How big should the buffer be?

PrepVia suggests planning eight to twelve weeks of coverage on China-sourced SKUs, calculated as weekly sales multiplied by the gap between your last pre-holiday arrival and your first post-holiday arrival, minus what is already in transit. That is a planning range from one company, not an Amazon rule, so test it against your own lead times and cash.

Where to Keep the Extra Stock: FBA or a US Warehouse

Ordering more is only half the plan. Sending all of it to Amazon at once can trade a stockout for higher fees or a blocked shipment. Three Amazon rules set the limits.

Stay above the 28-day floor

An Amazon team member explains on the Seller Forums that the low-inventory-level fee applies only when both the 30-day and 90-day historical days of supply are below 28 days. A thin buffer in February can trigger this fee on every unit shipped. Our article on the FBA low-inventory-level fee and days of supply explains the exemptions and how the metric is calculated.

Check your capacity limit before you ship

Forceget notes that Amazon sets a monthly capacity limit per storage type, based on factors such as your IPI score, sales history, and seasonality, and that you cannot create new shipments if your on-hand inventory plus open shipments would go over it. A big pre-holiday order may simply not fit. See our guide to FBA capacity limits and Capacity Manager for how limits are set and how to request more space.

Storage costs still add up

Standard-size monthly storage drops from $2.40 per cubic foot in October to December to $0.78 per cubic foot from January to September, according to Your eCom Team. That helps in January, but months of extra stock still cost money and keep aging.

Stage the rest and send it in waves

Both PrepVia and Forceget recommend the same pattern: keep roughly 30 to 60 days of supply at Amazon (PrepVia's range), land the rest at a US warehouse or prep center, and send smaller replenishments to FBA through February and March. Amazon's own option for this is Amazon Warehousing and Distribution. Our article on AWD bulk storage and auto-replenishment explains how it works and when it fits. Forceget also notes that US fulfillment centers operate normally during Chinese New Year; the bottleneck is that no new cargo leaves China.

Plan the Cash Before You Place the Order

Monthly budget sheets and a finance tracker planner with a gold pen and paper clips

For many sellers, the hard part is not the math. It is the money. PrepVia points out that the Chinese New Year freight bill lands in December and January, on top of post-holiday returns and before fourth-quarter payouts fully settle. A bigger order, a deposit, ocean freight, and possibly some air freight can all hit in the same few weeks.

Before you confirm the order, write down three numbers for each product:

  • The deposit and balance dates your supplier expects, and whether paying the balance is tied to inspection or shipping.
  • Freight and import costs for the shipment, including the higher rates forwarders expect before the holiday.
  • The sales you expect to bring in before each payment is due, using last year's January numbers rather than your Black Friday week.

If the cash does not cover every SKU, cover your best sellers first. A slower product that runs out in March costs far less than your top seller going out of stock for six weeks. Keep a small contingency budget, because Maersk notes that peak season surcharges and higher freight rates are common during these periods.

Protect Quality on Both Sides of the Holiday

Rush orders bring a second risk. China Quality Service warns that factories squeeze production into a short window before the holiday, run overtime, and bring on temporary staff, and that defect rates can climb right when there is no time left for rework. It also flags the first production runs after reopening as higher risk, because of new staff and restarted equipment.

A few habits reduce that risk:

  • Approve a golden sample early. Make sure the factory and any inspector know exactly what "correct" looks like.
  • Schedule the pre-shipment inspection now. Inspection firms get booked up in January too.
  • Check labels and cartons. Rushed final orders are where FNSKU and carton label mistakes happen, and an FBA shipment with labeling problems can be delayed at receiving.
  • Inspect the first post-holiday batch as carefully as you would a brand-new supplier.

Running Late? What You Can Still Do This Week

If you have not placed your pre-holiday order yet, you still have options, but each one costs more time or money:

  • Ask what the factory can still finish. A partial order shipped in December can be better than a full order that misses the last sailing.
  • Split by shipping mode. Send most of the stock by ocean and air-freight a smaller amount of your best seller to cover the gap. PrepVia estimates air at 5 to 10 times the cost of ocean, so keep air for products that would otherwise run out.
  • Place your first post-holiday order before the break. Forceget suggests placing post-holiday orders before factories close, so your order is in the queue when they reopen.
  • Slow down a product you cannot refill. If a SKU will clearly run out, think twice before putting it in a deep discount or a big ad push. Stretching the stock you have can keep the listing in stock longer.

Your Chinese New Year Checklist for This Week

Before the Black Friday rush takes all your attention, block one hour and do five things: send the seven supplier questions above to every factory you buy from; ask your freight forwarder for its last booking and sailing dates to your port; run the pre-holiday formula for each China-sourced SKU using last year's February and March sales; check your FBA capacity limit and decide how much will wait at a US warehouse; and map the deposit, balance, and freight payments against your expected cash. If you want a structured way to learn sourcing, shipping, and inventory planning, explore Bubba Academy and its Amazon training course.

🚀

Ready to Build an Amazon Business the Right Way?

Bubba Academy trains sellers on product research, sourcing, compliance basics, listings, FBA inventory, pricing, and ads, so you can plan your supply chain a season ahead.

Join Bubba Academy Today →

Frequently Asked Questions

When is Chinese New Year 2027?

Chinese New Year 2027 falls on Saturday, February 6, 2027. China's official Spring Festival holiday runs nine days, from February 5 to February 13, 2027, according to the State Council notice published in November 2026.

How long do Chinese factories close for Chinese New Year?

Much longer than the official holiday. Logistics firms report that many factories stop or slow production from mid- or late January and do not return to full capacity until late February or March. Each factory is different, so ask your supplier for its closing, reopening, and full-production dates in writing.

When should Amazon sellers place their last order before Chinese New Year 2027?

Logistics guides published in 2026 put the last purchase orders for ocean freight between early November and early December 2026, with last ocean departures from late December to early January. Your real deadline depends on your production time, destination port, and freight route, so confirm it with your supplier and forwarder.

How much extra inventory should I order before Chinese New Year?

One common method is daily sales multiplied by the factory gap plus transit time plus a safety margin, minus the stock you already have at Amazon and in transit. Use last year's February and March sales, not December's, and check that the result fits your cash and your FBA capacity limit.

Should I send all my pre-holiday stock straight to Amazon FBA?

Not always. Sending everything at once can exceed your capacity limit and add storage costs. Many sellers keep a few weeks to two months of supply at Amazon, stay above the 28-day level that can trigger the low-inventory-level fee, and store the rest at a US warehouse or AWD to send in smaller shipments.